UCMR 6 proposed
EPA proposed that water systems test for 30 more unregulated contaminants in 2028–2030, including seven “ultrashort” PFAS such as TFA. Comments closed August 31, 2026. Microplastics were left off the list.
The federal and Mississippi rules behind safe drinking water and clean rivers: the Safe Drinking Water Act, the Clean Water Act, every major drinking water rule, and what's changing with UCMR 5, UCMR 6, PFAS, and lead.
Rules make more sense once you see the pattern: Congress passes a law, EPA writes rules under it, and a state agency like MSDH or MDEQ enforces them. For the license exam, know the MCLs, the public notice tiers, and the coliform and lead rules. For the job, watch the dates on this page. 2027 is a big year: new Consumer Confidence Reports in January and the Lead and Copper Rule Improvements in November.
Status as of September 2026. A proposed rule can change before it's final, so check the linked EPA page before you act on it.
EPA proposed that water systems test for 30 more unregulated contaminants in 2028–2030, including seven “ultrashort” PFAS such as TFA. Comments closed August 31, 2026. Microplastics were left off the list.
EPA released the last UCMR 5 data: just under 2 million results for 29 PFAS and lithium from more than 10,000 water systems. EPA estimates about 7.8% of systems would have a running annual average above the PFOA or PFOS limit.
EPA proposed keeping the 4.0 ppt limits for PFOA and PFOS but moving their compliance date from 2029 to 2031, and rescinding the limits for PFHxS, PFNA, GenX (HFPO-DA), and the Hazard Index mixture. Until EPA finalizes those changes, the April 2024 rule is still the rule.
The D.C. Circuit heard arguments in the challenge to the 2024 PFAS standards (AWWA v. EPA). In January 2026 the court turned down EPA's request to drop the four Hazard Index PFAS limits without a full review.
A federal appeals court upheld EPA's 2024 designation of PFOA and PFOS as hazardous substances under CERCLA, the Superfund law.
EPA proposed a national standard for perchlorate, with a health goal of 20 µg/L and an enforceable limit of 20, 40, or 80 µg/L. A court order requires a final rule by May 21, 2027.
EPA and the Army Corps asked for more comment (due October 9, 2026) on how far Clean Water Act jurisdiction reaches after the Supreme Court's 2023 Sackett decision. Their November 2025 proposal would narrow the definition.
EPA is running an expedited review of fluoride under the Safe Drinking Water Act. The enforceable limit is still 4.0 mg/L. Utah and Florida banned adding fluoride to public water in 2025.
The revised CCR rule takes effect: easier-to-read reports, better lead information, translation help, and reports twice a year for systems serving 10,000 or more people.
The lead action level drops to 10 µg/L, most systems must replace every lead service line within 10 years, and first- and fifth-liter sampling begins.
EPA must propose revisions to the microbial and disinfection byproduct rules by July 30, 2027, and finalize them by October 2, 2028.
If the rule is finalized as proposed, sampling runs from January 2028 through December 2030.
A statute is a law passed by Congress, such as the Safe Drinking Water Act (SDWA) or the Clean Water Act (CWA). A statute tells EPA what to do. EPA then writes regulations, also called rules, that spell out the numbers, monitoring schedules, and reports. Rules are published in the Federal Register and collected in the Code of Federal Regulations (CFR).
| CFR (Title 40) | What it covers |
|---|---|
| Part 141 | National Primary Drinking Water Regulations: MCLs, treatment techniques, monitoring, public notice, CCRs |
| Part 142 | How states get and keep primacy |
| Part 143 | Secondary (aesthetic) standards, which are not federally enforceable |
| Parts 122, 131, 133 | Clean Water Act: NPDES permits, water quality standards, secondary treatment for sewage plants |
| Parts 403, 503 | Industrial pretreatment; sewage sludge and biosolids |
| Parts 68, 112, 355, 370 | Risk Management Program, oil spill prevention (SPCC), and community right-to-know (EPCRA) |
Primacy means a state runs the program itself. In Mississippi, the State Department of Health's Bureau of Public Water Supply has primacy for drinking water, and the Department of Environmental Quality (MDEQ) has run the Clean Water Act permit program (NPDES) since May 1, 1974.
Signed on December 16, 1974, the SDWA covers every public water system in the country. It does not cover private household wells. It has been amended several times:
EPA also re-examines every existing standard in a six-year review, which is how rules like the microbial and disinfection byproduct rules end up being revised.
A public water system (PWS) provides water for human consumption through pipes or other constructed conveyances to at least 15 service connections, or regularly serves at least 25 people at least 60 days a year. There are three kinds:
| Type | Definition | Examples |
|---|---|---|
| Community (CWS) | At least 15 connections used by year-round residents, or regularly serves at least 25 year-round residents | Towns, rural water associations, mobile home parks |
| Non-transient non-community (NTNCWS) | Regularly serves at least 25 of the same people at least 6 months a year | Schools, factories, and offices with their own water supply |
| Transient non-community (TNCWS) | Serves at least 25 people at least 60 days a year, but not the same people | Gas stations, campgrounds, rest areas, churches with their own well |
The type decides which rules apply. Community systems follow nearly all of them. Transient systems mostly worry about germs and nitrate, because their customers drink the water only briefly. A system that buys treated water from another system is a consecutive system. The seller, called the wholesale system, handles the treatment rules for its water, but the buyer is still responsible for its own distribution system.
Answer four questions to see the federal drinking water rules that apply, and why. Your MSDH regional engineer has the final word for your system.
Every major federal water rule on one screen. Search or filter, then open a card for the key numbers, what operators do, and the 2026 status.
The National Primary Drinking Water Regulations table, plus the PFAS limits and the secondary standards. Values in mg/L unless noted (1 mg/L = 1 ppm = 1,000 µg/L).
| Contaminant | MCL or TT | MCLG | Where it comes from / why it matters |
|---|
Source: EPA's National Primary Drinking Water Regulations (40 CFR 141) and secondary standards (40 CFR 143). The lead action level becomes 0.010 mg/L when the LCRI takes effect on November 1, 2027. The PFAS rows show the April 2024 rule; see the PFAS section for the 2026 proposals.
The Unregulated Contaminant Monitoring Rule comes from the 1996 SDWA amendments. Every five years EPA picks up to 30 contaminants that don't have drinking water standards yet and has water systems test for them. The results show how often, and at what levels, each one shows up nationwide. That data feeds the next regulatory determinations.
| Cycle | Sampling | Highlights |
|---|---|---|
| UCMR 1 | 2001–2005 | The first national screen of unregulated chemicals and microbes |
| UCMR 2 | 2008–2010 | Pesticides, flame retardants, explosives, nitrosamines |
| UCMR 3 | 2013–2015 | Six PFAS (including PFOA and PFOS), 1,4-dioxane, hexavalent chromium, chlorate, strontium, and two viruses at a small subset of systems |
| UCMR 4 | 2018–2020 | Ten cyanotoxins, manganese and germanium, pesticides, brominated haloacetic acids, alcohols, and other organics |
| UCMR 5 | 2023–2025 | 29 PFAS and lithium: the largest PFAS survey ever done |
| UCMR 6 | 2028–2030 (proposed) | Ultrashort PFAS such as TFA, pesticide metabolites, semivolatile and purgeable organics |
UCMR works with the Contaminant Candidate List (CCL), EPA's list of contaminants that may need regulation. The fifth list (CCL 5, final November 2022) named 66 chemicals, three chemical groups (PFAS, cyanotoxins, and disinfection byproducts), and 12 microbes.
Finalized December 27, 2021. Sampling ran from January 2023 through December 2025, and EPA released the final data on August 27, 2026.
PFAS were measured with EPA Methods 533 and 537.1, which overlap and together cover the 29 compounds. Lithium was measured with an inductively coupled plasma method. The reporting level for PFOA and PFOS was 0.004 µg/L (4 ppt). Search any compound below; tags show where it stands under the 2024 PFAS rule.
What EPA proposed, who would sample, and when. The list below is the proposal; the final rule can add, drop, or change contaminants.
PFAS (per- and polyfluoroalkyl substances) are thousands of man-made chemicals with very strong carbon–fluorine bonds. They're used in nonstick, stain-resistant, and waterproof products and in some firefighting foams. They barely break down in the environment, which is why they're nicknamed “forever chemicals.”
| Compound | MCLG | MCL |
|---|---|---|
| PFOA | Zero | 4.0 ppt (ng/L) |
| PFOS | Zero | 4.0 ppt |
| PFHxS | 10 ppt | 10 ppt |
| PFNA | 10 ppt | 10 ppt |
| HFPO-DA (“GenX chemicals”) | 10 ppt | 10 ppt |
| Mixtures of two or more of PFHxS, PFNA, HFPO-DA, and PFBS | Hazard Index of 1 | Hazard Index of 1 |
Community and non-transient non-community systems had three years (to 2027) for initial monitoring and five years (to 2029) to meet the MCLs. Compliance is based on a running annual average.
The Hazard Index adds up the ratio of each PFAS to its health-based water concentration. For example, PFHxS at 5 ppt is 5 ÷ 10 = 0.5 of the index. If the ratios for PFHxS, PFNA, HFPO-DA, and PFBS add up to more than 1, the mixture exceeds the standard.
Conventional treatment (coagulation, settling, filtration, chlorine) removes very little PFAS. Three technologies work: granular activated carbon (GAC), ion exchange resins made for PFAS, and reverse osmosis or nanofiltration membranes. Shorter-chain PFAS break through carbon sooner than PFOA and PFOS, and the ultrashort compounds on the UCMR 6 list are the hardest to remove. Spent carbon, resin, and membrane concentrate all need proper disposal.
Lead rarely comes from the source water. It gets into drinking water from lead service lines, lead solder, and brass fixtures, especially when the water is corrosive. So the rules focus on corrosion control, customer taps, and pipe replacement.
| Rule | What it did |
|---|---|
| Lead and Copper Rule (1991) | Action levels at the 90th percentile of tap samples: lead 0.015 mg/L, copper 1.3 mg/L. Exceeding one triggers corrosion control treatment, source water treatment, public education, and lead service line replacement. |
| Revisions (LCRR) (2021) | Required a service line inventory by October 16, 2024, added a 0.010 mg/L “trigger level,” find-and-fix follow-up at high-lead homes, and testing in schools and child care facilities. |
| Improvements (LCRI) (final October 2024, compliance November 1, 2027) | Lowers the lead action level to 0.010 mg/L and drops the trigger level. Requires most systems to replace all lead and “galvanized requiring replacement” service lines within 10 years, at an average of about 10% a year. Homes with lead lines are sampled at the first and fifth liter, and the higher result counts. Systems with repeated exceedances must make filters available. |
To find the 90th percentile, sort the tap results from lowest to highest and multiply the number of samples by 0.9. With 20 samples, 20 × 0.9 = 18, so the 90th percentile is the 18th result in that list.
Enacted on October 18, 1972, over a presidential veto, the Clean Water Act's goal is to “restore and maintain the chemical, physical, and biological integrity of the Nation's waters.” The SDWA protects the water coming out of the tap. The CWA protects rivers, lakes, streams, and wetlands, which are also the source water for surface water plants.
The CWA applies to “waters of the United States” (WOTUS). In Sackett v. EPA (May 25, 2023), the Supreme Court limited that to relatively permanent waters and wetlands with a continuous surface connection to them. EPA and the Army Corps issued a conforming rule in 2023, proposed a narrower definition in November 2025, and asked for more comment in September 2026.
In Mississippi, MDEQ issues NPDES permits and the Mississippi Commission on Environmental Quality adopts the state's water quality standards. MDEQ also publishes the state's water quality assessments, including its ground water quality assessment.
| Law or rule | What it means for a water utility |
|---|---|
| EPCRA (community right-to-know) | Chlorine is an extremely hazardous substance with a threshold planning quantity of 100 lb. Facilities storing that much or more must notify emergency planners and file a Tier II inventory report by March 1 each year. |
| OSHA Process Safety Management (29 CFR 1910.119) | Applies to processes with 1,500 lb or more of chlorine. It covers process hazard analysis, operating procedures, training, and management of change. Publicly owned utilities follow it where the state has an OSHA-approved plan covering public employers. |
| EPA Risk Management Program (40 CFR 68) | Applies to processes with more than 2,500 lb of chlorine (sulfur dioxide 5,000 lb; anhydrous ammonia 10,000 lb). Requires a hazard assessment, a prevention program, emergency response, and a risk management plan filed with EPA. |
| OSHA confined spaces (29 CFR 1910.146) | Permit-required confined space entry for tanks, vaults, and wet wells. |
| SPCC (40 CFR 112) | Oil spill plans where aboveground oil storage exceeds 1,320 gallons (counting containers of 55 gallons or more) or buried storage exceeds 42,000 gallons, and a discharge could reach navigable waters. Generator fuel tanks count. |
| CERCLA (Superfund) | PFOA and PFOS are hazardous substances (2024 designation, upheld in August 2026). This affects cleanup liability for contaminated sites. |
| Underground Injection Control (SDWA Part C) | Regulates six classes of injection wells to protect underground sources of drinking water. |
| Sole source aquifers (SDWA §1424(e)) | EPA can designate an aquifer that supplies at least half of an area's drinking water. Federally funded projects in the area then get EPA review. |
| “Lead free” (SDWA §1417) | Since 2014, pipes, fittings, and fixtures may average no more than 0.25% lead on wetted surfaces, and solder and flux no more than 0.2%. |
| AWIA Section 2013 | Community systems serving more than 3,300 people must complete a risk and resilience assessment, review it every five years, and update their emergency response plan within six months of each assessment. They certify both to EPA. |
The Drinking Water SRF (1996) and Clean Water SRF (1987) lend money at low interest, and some goes out as principal forgiveness for disadvantaged communities. The Bipartisan Infrastructure Law (November 15, 2021) added more than $50 billion for water, including $15 billion for lead service line replacement and $10 billion to address emerging contaminants such as PFAS. WIFIA (2014) makes long-term federal loans for large projects.
Cybersecurity: there is no federal cybersecurity rule for water systems yet. EPA withdrew its 2023 memo that would have added cybersecurity to sanitary surveys after states challenged it in court. EPA still offers free assessments and guidance, and AWIA risk assessments must consider cyber threats.
| Agency | Role |
|---|---|
| MSDH Bureau of Public Water Supply | Runs the Safe Drinking Water Act program under state law (the Mississippi Safe Drinking Water Act of 1997, Miss. Code §41-26). It approves plans for new and modified systems, tracks monitoring and violations, inspects systems in sanitary surveys, issues boil water notices, certifies operators, and runs the state's cross-connection control and emergency-plan requirements. |
| MDEQ (Department of Environmental Quality) | Issues NPDES and stormwater permits, sets water quality standards through the Commission on Environmental Quality, issues surface water and ground water withdrawal permits, licenses water well contractors, runs dam safety, and studies the state's aquifers through its Office of Land and Water Resources. |
| YMD (Yazoo Mississippi Delta Joint Water Management District) | Formed in 1989 after the 1988 drought. It processes agricultural water use permits in the Delta, measures water levels in the alluvial aquifer, and promotes irrigation efficiency. |
| EPA Region 4 (Atlanta) | Oversees Mississippi's programs and can act directly, for example with emergency orders under SDWA Section 1431. |
State law declares that all water, “whether occurring on the surface of the ground or underneath the surface of the ground,” belongs to the people of Mississippi and is subject to regulation (Miss. Code §51-3-1). A ground water withdrawal permit from MDEQ is required for wells with a surface casing 6 inches or more in diameter. A well serving a single household for domestic use is exempt. Wells that are part of a public water system must also meet MSDH rules, whatever their size.
In late August 2022, problems at Jackson's O.B. Curtis treatment plant left much of the city without reliable water pressure. The U.S. Department of Justice brought a Safe Drinking Water Act case, and on November 29, 2022, a federal court appointed an interim third-party manager, Ted Henifin, to run the system. His company, JXN Water, operates it under the court's order, which was later expanded to the sewer system. As of 2026 the court is still overseeing the system, and questions about the transition to long-term local control are before the judge.
The laws, rules, and court decisions that shaped today's requirements, and the deadlines still ahead.
Plain-language definitions from the LearnWater glossary.
Random questions about the rules on this page. Try a few rounds; each one draws a new set.
Greg answers from his built-in knowledge, right in your browser. Ask him to search EPA, NRWA, or MsRWA, and only your search words go to that site.
Rules change. These pages have the current text and dates.